Sprint Structure
YeboLearn operates on a 2-week sprint cycle that balances feature development with quality assurance and continuous deployment. This structure enables predictable delivery while maintaining technical excellence.
Sprint Overview
Two-Week Cadence
Why 2 Weeks?
- Long enough to complete meaningful features
- Short enough for rapid feedback and iteration
- Aligns with bi-weekly production releases
- Maintains team focus and momentum
Sprint Timeline:
Sprint N (2 weeks)
├─ Week 1: Development Sprint
│ ├─ Day 1 (Mon): Planning & kickoff
│ ├─ Day 2-5: Active development
│ └─ Code freeze: Friday 5 PM
├─ Week 2: Release Sprint
│ ├─ Day 6-7 (Mon-Tue): Testing & demos
│ ├─ Day 8-9 (Wed-Thu): Release prep & deploy
│ └─ Day 10 (Fri): Monitoring & retrospective
└─ Next sprint planning beginsSprint Ceremonies
Sprint Planning (Monday Week 1, 10 AM - 12 PM)
Participants: Entire engineering team, product owner, design lead
Agenda:
1. Sprint Review (15 minutes)
What We Shipped Last Sprint:
✅ AI quiz generator (10 story points)
✅ Payment retry logic (5 points)
✅ Performance optimizations (8 points)
Total: 23 points delivered (target was 32)
What Didn't Ship:
❌ Essay grading UI (9 points) - moved to this sprint
Why: Design changes required mid-sprint
Key Metrics:
• Velocity: 23 points (below average)
• Test coverage: 71% → 73%
• Deployment frequency: 8 deploys
• Production incidents: 1 (resolved in 20 min)2. Backlog Review (30 minutes)
Product owner presents prioritized backlog:
# Sprint 25 Proposed Work
## Theme: AI Essay Grading Launch
### High Priority (Must Have)
1. Essay Grading UI Component (9 pts)
- Student submission interface
- Real-time feedback display
- Revision tracking
2. AI Grading Backend (13 pts)
- Gemini integration for analysis
- Rubric-based scoring
- Feedback generation
- Rate limiting
3. Teacher Dashboard Updates (5 pts)
- View student submissions
- Manual grade override
- Bulk operations
### Medium Priority (Should Have)
4. Performance Optimization (5 pts)
- Database query caching
- Image optimization
- Bundle size reduction
5. Bug Fixes (3 pts)
- Login redirect issue
- Quiz timer accuracy
- Mobile responsiveness
### Nice to Have (If Capacity)
6. Analytics Improvements (3 pts)
7. Documentation Updates (2 pts)3. Story Breakdown & Estimation (60 minutes)
Team breaks down stories into technical tasks:
# Story: AI Grading Backend (13 points)
## Tasks:
- [ ] Design database schema for submissions (2 pts)
- [ ] Create submission API endpoint (2 pts)
- [ ] Integrate Gemini API (3 pts)
- [ ] Implement rubric scoring logic (2 pts)
- [ ] Build feedback generation (2 pts)
- [ ] Add rate limiting (1 pt)
- [ ] Write unit tests (1 pt)
## Technical Considerations:
- Need to handle long essays (10k+ words)
- Gemini API has 60 requests/minute limit
- Database migration required
- Async processing for >5 min operations
## Acceptance Criteria:
- [ ] Student can submit essay
- [ ] AI generates feedback within 30 seconds
- [ ] Feedback includes score and suggestions
- [ ] Teacher can review and override
- [ ] Error handling for API failuresEstimation Scale (Fibonacci):
1 point = 1-2 hours (simple bug fix)
2 points = Half day (straightforward feature)
3 points = 1 day (moderate complexity)
5 points = 2-3 days (complex feature)
8 points = 1 week (very complex, consider splitting)
13 points = 2 weeks (epic, must split into smaller stories)4. Sprint Commitment (15 minutes)
# Sprint 25 Commitment
## Sprint Goal
Launch AI essay grading feature with teacher oversight
## Committed Stories (32 points)
✓ Essay Grading UI (9 pts) - Sarah
✓ AI Grading Backend (13 pts) - John & Lisa
✓ Teacher Dashboard (5 pts) - Mark
✓ Performance Optimization (5 pts) - Sarah
## Stretch Goals (6 points)
○ Bug Fixes (3 pts) - Team
○ Analytics Improvements (3 pts) - Mark
## Dependencies & Risks
⚠️ Gemini API quota increase (requested, pending)
⚠️ Design for teacher dashboard (due Tuesday)
✓ Database migration tested in stagingOutputs:
- Sprint goal defined
- Stories committed (realistic velocity)
- Initial task assignments
- Dependencies identified
- Risks documented
Daily Standup (Every Day, 9:30 AM - 9:45 AM)
Format: Async-First with Sync Option
Async Update (Slack #engineering, before 9:30 AM):
Sarah | Yesterday | Today | Blockers
------|-----------|-------|----------
✅ Completed essay submission UI | Working on feedback display component | None
John | Yesterday | Today | Blockers
-----|-----------|-------|----------
✅ Set up Gemini API integration | Building rubric scoring logic | Waiting on API quota increase
Lisa | Yesterday | Today | Blockers
-----|-----------|-------|----------
✅ Reviewed John's PR, started rate limiting | Completing rate limiting, writing tests | None
Mark | Yesterday | Today | Blockers
-----|-----------|-------|----------
🚧 Teacher dashboard 70% done | Finishing dashboard, need design for grade override | Waiting on design from EmilySync Standup (Google Meet, 9:30 AM, 15 min max):
- Discuss blockers only
- Quick coordination needed
- Technical questions
- Not a status report (that's async)
Best Practices:
- Keep it brief (<2 min per person)
- Focus on coordination, not reporting
- Raise blockers immediately
- Help each other solve problems
- Skip if no blockers (async is enough)
Mid-Sprint Check-in (Wednesday Week 1, 3 PM - 3:30 PM)
Purpose: Course-correct if needed
Agenda:
1. Progress Review (10 min)
Sprint Burndown:
Day 1-2: 32 points remaining
Day 3-4: 21 points remaining (on track)
Day 5: 15 points remaining (slightly ahead)
Completed:
✅ Essay submission UI (9 pts)
✅ Database schema & migration (2 pts)
✅ Submission API endpoint (2 pts)
In Progress:
🚧 Gemini API integration (3 pts) - 80% done
🚧 Rubric scoring (2 pts) - 50% done
🚧 Teacher dashboard (5 pts) - 60% done
Not Started:
⏳ Performance optimization (5 pts)
⏳ Feedback generation (2 pts)2. Risk Assessment (10 min)
Resolved:
✅ Gemini API quota approved
✅ Design specs delivered
New Risks:
⚠️ Teacher dashboard taking longer than expected
→ Mitigation: Mark pairing with Sarah tomorrow
⚠️ Gemini API response time slower than expected (45s)
→ Mitigation: Investigating caching strategy3. Adjustments (10 min)
- Move performance optimization to stretch goals
- Add performance spike for next sprint
- All other work on track
Sprint Demo (Thursday Week 2, 3 PM - 4 PM)
Participants: Engineering, product, design, stakeholders
Format: Show Working Software
Demo Script:
# Sprint 25 Demo - AI Essay Grading
## 1. Student Experience (Sarah - 10 min)
[Live demo]
- Submit essay on "Climate Change Impact"
- Real-time progress indicator
- Receive AI feedback in 30 seconds
- Review detailed suggestions
## 2. AI Grading Engine (John - 10 min)
[Technical walkthrough]
- Gemini API integration
- Rubric-based scoring algorithm
- Example: Essay analysis breakdown
- Performance: 30s average, 45s max
## 3. Teacher Dashboard (Mark - 10 min)
[Live demo]
- View student submissions
- Review AI-generated feedback
- Override grades if needed
- Bulk actions for classes
## 4. Platform Improvements (Team - 5 min)
- Page load time: 2.2s → 1.8s
- Test coverage: 73% → 76%
- Fixed login redirect bug
## 5. Metrics & Impact (Product - 5 min)
- Feature ready for beta (100 students)
- Expected to save teachers 5 hours/week
- Differentiated feature (no African competitor has this)
## 6. Q&A (10 min)Demo Best Practices:
- Show working features in production/staging
- Focus on user value, not technical details
- Highlight metrics and business impact
- Be honest about what's not done
- Gather feedback for next iterations
Sprint Retrospective (Friday Week 2, 2 PM - 3 PM)
Format: Start-Stop-Continue + Action Items
1. What Went Well? (15 min)
✅ Excellent collaboration on AI grading
- John and Lisa pair programming was very effective
- Shipped complex feature with high quality
✅ Mid-sprint check-in caught teacher dashboard risk early
- Adjusted plan and paired to recover
✅ Test coverage improved to 76%
- Everyone writing tests first more consistently2. What Didn't Go Well? (15 min)
❌ Initial estimates for teacher dashboard were too optimistic
- Didn't account for complex permission logic
- Need to break down UI stories more thoroughly
❌ Gemini API performance concerns discovered late
- Should have spiked this in previous sprint
- Need better upfront research for external APIs
❌ Two PRs sat unreviewed for >1 day
- Team was too focused on own work
- Need better PR review discipline3. Action Items (20 min)
🎯 Action: Create spike story for researching external APIs
Owner: John
Due: Next sprint planning
🎯 Action: Add "PR review time" to daily standup check
Owner: Team
Due: Ongoing, starting Monday
🎯 Action: Update estimation guide with UI complexity checklist
Owner: Sarah
Due: End of next sprint
🎯 Action: Schedule AI performance optimization spike
Owner: Lisa
Due: Sprint 264. Celebrate Wins (10 min)
- First AI grading feature shipped
- Best test coverage yet (76%)
- Zero production incidents
- Team collaboration highlighted
Retrospective Rotation:
- Different facilitator each sprint
- Rotate format (timeline, sailboat, 4Ls, etc.)
- Track action items completion
- Review past action items
Sprint Metrics
Velocity Tracking
Story Points Completed Per Sprint:
Sprint 20: 34 points
Sprint 21: 38 points
Sprint 22: 32 points (holiday)
Sprint 23: 40 points
Sprint 24: 36 points
Sprint 25: 38 points (current)
Rolling Average (last 6 sprints): 36 points
Target for Planning: 32-36 pointsVelocity Trends:
Increasing Velocity:
✓ Team growing in experience
✓ Better estimation accuracy
✓ Improved tooling and automation
Decreasing Velocity:
⚠️ Technical debt accumulating
⚠️ Complex features increasing
⚠️ More interruptions/supportSprint Health Metrics
Commitment Accuracy:
Sprint 25:
Committed: 32 points
Delivered: 38 points
Accuracy: 119% (over-delivered due to stretch goals)
Target: 90-110% (consistent delivery)Scope Change During Sprint:
Sprint 25:
Added: 6 points (urgent bug fix)
Removed: 0 points
Net Change: +6 points
Target: <10% scope changeSprint Goal Achievement:
Sprint 25 Goal: Launch AI essay grading feature
Result: ✅ Achieved (feature in beta)
Historical Achievement Rate: 87% (last 10 sprints)
Target: >80%Quality Metrics
Defect Escape Rate:
Bugs Found in Production (from this sprint):
Sprint 25: 2 minor bugs
Sprint 24: 1 critical, 3 minor
Sprint 23: 0 bugs
Target: <3 bugs per sprintTest Coverage:
Sprint 25: 76% (↑3% from Sprint 24)
Sprint 24: 73%
Sprint 23: 71%
Target: Maintain >70%, trend upwardCode Review Metrics:
Average PR Review Time: 3.2 hours
PRs Requiring Multiple Review Rounds: 35%
PRs Approved Without Changes: 12%
Targets:
- Review time <4 hours
- Multiple rounds acceptable (thorough review)
- Some changes expected (quality gate)Sprint Success Patterns
High-Performing Sprints
Characteristics:
- Clear, focused sprint goal
- Well-estimated stories (no surprises)
- Minimal scope changes
- Fast PR review cycle
- Strong team collaboration
- Proactive communication
Example: Sprint 23 (40 points delivered)
What Made It Great:
✓ Focused theme: Performance optimization
✓ Technical debt sprint (motivated team)
✓ All stories well-understood upfront
✓ No external dependencies
✓ Pair programming on complex work
✓ Daily async updates kept everyone aligned
Result:
• 40 points delivered (highest velocity)
• Zero production bugs
• Test coverage +5%
• Team satisfaction: 9/10Struggling Sprints
Warning Signs:
- Unclear or conflicting goals
- Large stories (>8 points)
- Many external dependencies
- Mid-sprint scope additions
- PRs sitting unreviewed
- Team working in silos
Example: Sprint 22 (32 points, missed goal)
What Went Wrong:
❌ Holiday week (reduced capacity)
❌ External dependency blocked work (Gemini API changes)
❌ Underestimated complexity of payment refactor
❌ Mid-sprint production incident (2 days lost)
❌ Design changes required rework
Lessons Learned:
• Account for holidays in planning
• Spike external API changes upfront
• Break down payment work more granularly
• Build incident response time into estimates
• Lock designs before sprint startsSprint Anti-Patterns to Avoid
Over-Commitment
Problem: Committing to 50 points when velocity is 35
Result: Rush, cut corners, incomplete features, burnout
Solution:
• Use conservative estimates
• Build in buffer (80% of available capacity)
• Protect quality over quantity
• Use stretch goals for extra capacityUnder-Commitment
Problem: Committing to 20 points when velocity is 35
Result: Waste capacity, slow delivery, team boredom
Solution:
• Commit to realistic capacity
• Have ready backlog items
• Add stretch goals
• Trust the team's abilityScope Creep
Problem: Adding 10 stories mid-sprint
Result: Lose focus, miss sprint goal, context switching
Solution:
• Strict scope freeze after planning
• Critical bugs only exception
• New work goes to next sprint
• Communicate trade-offs clearlyPoor Story Breakdown
Problem: Stories >13 points, unclear acceptance criteria
Result: Can't complete in sprint, unclear when "done"
Solution:
• Break stories to <8 points
• Define clear acceptance criteria
• Include technical tasks
• Consider edge cases upfrontSprint Planning Tips
Effective Estimation
Planning Poker:
1. Product owner reads story
2. Team asks clarifying questions
3. Everyone estimates privately (cards)
4. Reveal simultaneously
5. Discuss high/low estimates
6. Re-estimate until consensus
7. Move to next storyEstimation Calibration:
Reference Stories (Historical):
1 point: "Fix typo in error message"
2 points: "Add email validation"
3 points: "Build simple CRUD endpoint"
5 points: "Integrate external API with error handling"
8 points: "Build complex UI with state management"
13 points: "Too large - split it up"When Uncertain:
- Add buffer (round up)
- Create spike story (time-boxed research)
- Break into smaller, better-understood pieces
- Defer to next sprint for more research
Story Readiness
Definition of Ready:
- [ ] User value is clear
- [ ] Acceptance criteria defined
- [ ] Dependencies identified
- [ ] Design complete (if UI work)
- [ ] Technical approach discussed
- [ ] Estimatable by team
- [ ] Small enough for one sprint
If Not Ready:
- Don't commit to sprint
- Schedule backlog refinement
- Get design/product input
- Create spike for research
Related Documentation
- Planning Overview - Overall planning process
- Backlog Management - Story writing and grooming
- Estimation Guide - Detailed estimation methodology
- Development Workflow - Daily execution